41 – Bringing Our New Home, Home.

Before we could move the 5th wheel to it’s temporary home we had to run water and septic lines. We also wanted a frost free valve for easy water access by the trailer. After backfilling and lots of careful measuring to be sure we didn’t drive on top of the...

40 – Rolling With Changes

We are so used to this adventure twisting and turning, we’d probably have heart attacks if even one thing went as planned. The plan was to be completely moved out of Havasu by April 2017 and into the new house. Lofty goal indeed. The more we pushed, the more it...

39 – Septic Install

    The design called for so much leach rock below the 4″ perforated pipe and so much topsoil above it. The pipe needs to be completely level across all 130 feet of leach field so we started by marking lines in the trench using a laser. There was...
38 – Septic Dig

38 – Septic Dig

The huge leach field required really was bad news. The digging in this area is terrible at best and would surely put plenty of wear and tear on our beloved backhoe. We’ve learned that properly sizing tools to a particular job saves both time and money in the...
37 – Septic Design

37 – Septic Design

Now that we had water plumbed to the home site we needed a place for wastewater to safely go. Even though I’m a “do it yourselfer” there are times when you need to call in a professional. We hired out the design phase to an engineering firm that...
36 – Rock Hard Digging

36 – Rock Hard Digging

We needed a pad high enough to clear any winter shade for the greenhouse and had also gathered a large collection of rocks from all our digging projects that needed a home. We brought in another D8 for the cut and filled it with all our leftover material plus about 80...